Open topic with table of contents
Schedule an Existing Batch Renewal Group
If you created a batch renewal group and did not schedule it for processing, follow these steps to schedule the group for batch processing.
To schedule an existing batch renewal group:
- On the main RCT Express page, click the Tools link. The Tools page appears.
- Click the Group Processing link. The Group Processing page appears.
- Click the Manage Group(s) link. The Current Groups page appears.
- Find the group that you want to schedule and click the Schedule link.
- On the Schedule page, do one of the following:
- To process the group next time batch processing is scheduled to run, select Schedule A.S.A.P.
- To specify the date that you want to process the group, select Set Desired Date and enter the date in MM/DD/YYYY format. To select the date from a calendar, click the Select Date icon.
- Click Schedule Group.
Help file last modified: 7/26/2018