Cost Data Settings

The RCT quarterly cost data updates can be scheduled by going to Tools > Configuration Settings > Cost Data Settings.

The screen shows the currently installed cost data set and the newest available set, as well as a table of completed and pending updates.

To schedule an update:

  1. Enter a planned date for the update.
  2. Enter the planned time. Time can be selected in 30 minute increments.
  3. Select the users that you want to be notified of the update. (The list shows all Admin users on the site). Notifications will be sent to selected users when a new cost data update is scheduled, cancelled, or successfully completed.
  4. Click Schedule Update. The update will now be shown in the table as Pending. Once the update takes place, it will show in the table as Completed.

Note: If you don't want to manually schedule updates, you can have CoreLogic configure the updates to occur automatically. The table will show all pending and completed updates.

To cancel a pending update:

  1. Click the Cancel Update button under the currently scheduled update planned date and time. Or in the table click the X under Actions for the pending update that you want to cancel.
  2. An "Are you sure?" dialog will appear. Click Yes to cancel the update or No if you do not want to cancel the update.
  3. A cancelled update can then be rescheduled. Selected users are notified of the cancelled update.

Only one cost data update at a time can be pending.